top of page
US Zen Institute Construction Progress
Construction is progressing smoothly with the US Zen Institute Relics Addition thanks to close collaboration between the contractor and architect...

January 31, 2026
Starting the footings and foundation of the Relics Addition during extremely cold weather was a challenge that was met by Hubert Construction and their concrete subcontractor..

February 27, 2026
CMU block and reinforced concrete foundation walls along with the reinforced concrete slab were installed after the footings passed inspection. Sub-grade foundation drains and waterproofing were installed.

April 2, 2026
Steel frame has been erected and all welds inspected. Framing starts next.
bottom of page
