top of page

US Zen Institute Construction Progress

Construction is progressing smoothly with the US Zen Institute Relics Addition thanks to close collaboration between the contractor and architect...

USZI 2026 01a.jpg

January 31, 2026

Starting the footings and foundation of the Relics Addition during extremely cold weather was a challenge that was met by Hubert Construction and their concrete subcontractor..

USZI 2026 03.jpg

February 27, 2026

CMU block and reinforced concrete foundation walls along with the reinforced concrete slab were installed after the footings passed inspection.  Sub-grade foundation drains and waterproofing were installed.

USZI 2026 04.jpg

April 2, 2026

Steel frame has been erected and all welds inspected.  Framing starts next.

bottom of page